    Church Building Expansion - The Plan
Phases
Phase one: 
1. Multipurpose Activity Center:  Indoor Gym   
2. Bathrooms for multipurpose activity center
3. Bathroom fittings for the new chapel
4. Foundation for classrooms/office/new chapel
5. Circular driveway (paved, one direction)
Phase two A: 
Built Entire shell.
Phase two B: 
Complete 14 new classrooms, 4 new offices.
 Phase Three: 
1. Complete the New Chapel with 355 seats.
2. Improve gravel parking lot.
Timeline for Phase One and Phase Two A
- Project promotion & fundraising, 
 Dec 2021
- Design and Build Contractor searching, Apr 2022 
- Detail design for building permit, 
 Sept 2022
- Apply for building permit, 
 Jun 2023
- Building permit Approval, 
 Apr 2024
- Construction begins, 
 May 2024
- Construction complete, 
 Dec 2024
- Building occupancy approval, 
 Jan 2025